AQW 27463/22-27 Written question to the Minister for the Economy
To ask the Minister for the Economy to detail (i) any Departmental or Ministerial decisions taken in relation to the Mourne Gateway Project; and (ii) when these decisions were taken.
Asked by Andrew McMurray MLA on 20 May 2025
- Answered
- Written
- Tabled
- 20 May 2025
- Answer due by
- 5 June 2025
- Answered
- 30 May 202510 days after tabling
- Department
- Department for the Economy
- Priority question
- No
Answer
Minister Lyons approved Newry Mourne and Down District Council’s Outline Business Case (OBC) for the Mourne Mountains Gateway Project on 19 November 2021.
Due to changes that occurred over the passage of time, an update to the OBC was prepared by Council and approved by the Department’s Permanent Secretary on 19 March 2024, following which the Department awarded a contract for funding for the project in May 2024.