AQW 41600/22-27 Written question to the Minister of Education

To ask the Minister of Education to detail a timeline for the delivery of the School Enhancement Project for St. Mary's Primary School, Barr.

Asked by Andrew McMurray MLA on 27 February 2026

  • Answered
  • Written
Tabled
27 February 2026
Answer due by
16 March 2026
Answered
6 March 20267 days after tabling
Department
Department of Education
Priority question
No

Answer

The tender evaluation process for the construction of the School Enhancement Programme (SEP) project at St. Mary’s Primary School, Barr, has been completed by the Integrated Consultancy Team (ICT) and a tender report has been sent to my department for review.

Following successful completion of this review my department will proceed with the appointment of a contractor. Once a contractor is appointed, they will develop a programme including a project timeline.

Official sources